Regulation · 04 · Gaps

Open questions: what is still unresolved for launching communities

The law recognised communities and the NEURC draft described the core procedure, but between them and the first real bill lie questions no act answers today. This list shows who should settle each one and whether a proposal exists.

Not regulated
Checked against sources
21 Nov 2026
Reading time
3 min

List of gaps

Questions without an answer in current acts
QuestionWhere it should be settledState on 21 Nov 2026Wesfin proposal
How the virtual community metering point is created and changedMetering Code, administrator rulesOnly mentioned in the draft (p. 10.3.7)GEO-02
How a community and third parties obtain members’ dataMetering Code (Law Art. 53(6))The law requires it, no procedure yetGEO-05, GEO-SUP-04
“Fair payment” for DSO cooperation with communitiesRegulator’s procedure (Art. 58-2(3))Not set–
How a DSO confirms electrical proximity of metering pointsDistribution CodeNot regulatedGEO-SUP-08
A tariff for sharing over the DSO networkNEURC tariff methodologyThe draft refers to general tariffsGEO-TAR-01, GEO-TAR-02
The role of an independent community administratorRetail rulesAbsent from the draftGEO-SUP-01
The line between allocation and licensed supply or distributionRetail rules, licence conditionsThe draft lists “distribution” among community activitiesGEO-SUP-05
Community, aggregator and BRP roles on imbalancesMarket Rules, retail rulesThe draft names two options onlyGEO-01, GEO-07
How communities take part in market segmentsRegulator’s procedure (Art. 58-2(5))Not set separatelyGEO-01
Specifics for condominium associations as active consumersRegulator’s decision (Art. 58-1(8))Status to be checked–
Peer-to-peer trading procedureRegulator’s procedure (Art. 58-1(11))Not set–
Taxation of communities and internal settlementTax Code, tax authority guidanceNo specific rules–
Corrections to past periods and member disputesMetering Code, retail rulesNot described for communitiesGEO-03, GEO-09

What blocks launch most

  1. Data. Without a virtual metering point procedure and data access there is no share calculation and no way to check a bill. This is a Metering Code issue, not only chapter 10.3.
  2. Tariff. Without a basis for a differentiated tariff, households often get no economic case for a community (see economics).
  3. Roles. Without an administrator role every small community must be its own IT operator, and without clear imbalance roles suppliers and BRPs will not sign contracts.

How and in what order these can be solved: Reforms needed.

Sources

  1. Law No. 2019-VIII, Arts. 53, 58-1, 58-2 (in Ukrainian) (opens in a new tab) · Verkhovna Rada of Ukraine
  2. NEURC draft resolution of 4 Nov 2026 (in Ukrainian) (opens in a new tab) · NEURC

    A draft, not adopted.

  3. Commercial Metering Code (No. 311, in Ukrainian) (opens in a new tab) · NEURC
  4. Distribution System Code (No. 310, in Ukrainian) (opens in a new tab) · NEURC
  5. Wesfin Flex submission No. 59 (Ukrainian) · Wesfin Flex LLC
  6. Wesfin Flex submission No. 66 (Ukrainian) · Wesfin Flex LLC

This is an explanatory text by Wesfin, not legal advice. Legal acts are quoted from official texts as of the check date; verify the current version before acting.