Learn · 04
How Europe does it: Austria, Portugal, Spain, Italy and others
EU law gives communities the right to share energy, but each country decides how shares are counted, how the grid is paid for and how investment is encouraged. We compared four models using official sources.
The EU frame: two community models and a right to share
The 2019 Clean Energy for All Europeans package introduced energy communities into EU law. Directive (EU) 2019/944 (opens in a new tab) on the internal electricity market defines citizen energy communities and their right to share energy among members. Directive (EU) 2018/2001 (opens in a new tab) (RED II) defines renewable energy communities. Directive (EU) 2024/1711 (opens in a new tab) extended the right to energy sharing to active customers.
As an Energy Community contracting party, Ukraine transposes these rules: the community energy organisation in the Law on the Electricity Market corresponds to the citizen energy community, and the renewable energy community under Law No. 4963-IX to the RED II model.
Comparison table
| Austria | Spain | Portugal | Italy | |
|---|---|---|---|---|
| Who shares | Energy communities (EEG, BEG), joint energy use under the ElWG | Collective self-consumption (RD 244/2019) | Collective self-consumption, renewable energy communities (DL 15/2022) | Renewable energy communities (CER), self-consumer groups |
| Proximity limit | Zones: same transformer (local), same DSO substation (regional), beyond that no reductions | Interior network, same LV transformer, under 500 m or same cadastral reference | Set by ERSE rules for self-consumption through the public grid (RESP) | The area of one primary substation (cabina primaria) |
| Metering and allocation | 15-minute values; dynamic allocation by default | Agreed coefficients, fixed or hourly, summing to 1 | Through a designated manager (EGAC) | “Shared energy” calculated by the operator GSE |
| Network tariff | Reduced variable network rate in the local and regional zones; set yearly by E-Control | Energy passing through the grid pays network components | Network access tariffs charged on shared energy; no losses applied | Normal network tariff; an incentive on shared energy |
| Main incentive | Lower network charges; exemption from certain levies for EEG | Simplified surplus compensation up to 100 kW | A tariff reflecting the networks used | A premium of €60–120/MWh for 20 years + a PNRR grant |
Austria: the tariff depends on where in the grid you share
Austria has the most developed model built on electrical proximity. Since 1 October 2026 new provisions of the ElWG apply, under which network tariffs for joint energy use are determined no longer by the type of model but by the proximity zone (Nahebereich) each model selects at registration.
| Zone | What is shared | Network levels used | Network reduction |
|---|---|---|---|
| Local | The same transformer station (low-voltage side); in practice a 1–2 km radius | Levels 6 and 7 | Reduced variable rate (Netzarbeitspreis) |
| Regional | The same substation (Umspannwerk) of one operator, medium voltage; in practice up to ~30 km | Levels 4–7 | Reduced variable rate, smaller reduction |
| Bidding zone | Several substations or operators | Levels 1–7 | No reduction |
- Until the end of 2026 only members of local and regional renewable energy communities (EEG) receive the reduced variable rate. Extension to other models (citizen communities BEG, peer-to-peer agreements) is expected with the revised SNE-VO from 1 Jan 2027.
- Exemption from the electricity levy and the renewable support contribution still applies only to EEG (ElWG § 68).
- Allocation in all models uses 15-minute smart-meter values. Dynamic allocation is the default; static allocation is no longer offered to new communities.
Lesson for Ukraine: proximity should follow grid topology confirmed by the operator, not distance on a map, and the size of the reduction should be a separate, annually reviewed tariff decision of the regulator. This is the logic of the Wesfin concept.
Spain: simple proximity criteria and agreed coefficients
Spain’s collective self-consumption (Royal Decree 244/2019) treats a plant as “near” consumers if one condition holds: it is connected to the consumers’ interior network or by direct lines; to low-voltage networks fed by the same transformer station; it is within 500 m (between metering devices); or it shares the same cadastral reference (first 14 digits).
Participants sign an agreement with allocation coefficients: fixed for the year or hourly, set in advance and summing to 1. The basis may be contracted capacity, capital contribution or another criterion agreed by all. Surplus from plants up to 100 kW can be compensated under a simplified mechanism.
Lesson for Ukraine: clear, verifiable proximity criteria a consumer can assess before investing, and an algorithm fixed in advance for every interval.
Portugal: a designated manager and tariffs on shared energy
Decree-Law 15/2022 transposed renewable self-consumption into Portuguese law. The regulator ERSE adopted a dedicated self-consumption regulation. Collective self-consumption schemes and renewable energy communities appoint a collective self-consumption manager (EGAC), responsible for allocation and dealing with the network operator.
- When shared energy passes through the public grid (RESP), network access tariffs are charged on it, collected by the network operator from the EGAC and set in ERSE’s tariff regulation.
- Consumption of shared energy is not subject to network losses.
- Residual supply to members is paid at normal tariffs.
Lesson for Ukraine: an independent community manager as a defined role with clear duties towards the operator, and a network tariff applied to the shared energy specifically. This echoes Wesfin Flex proposal GEO-SUP-01 on a community’s authorised agent.
Italy: a premium on shared energy and grants for small municipalities
Italy encourages communities not with a network discount but with a premium on every MWh of shared energy. All members of a renewable energy community must be within the area of one primary substation (cabina primaria); each plant is limited to 1 MW.
| Plant size | Fixed part | Variable part | Extra |
|---|---|---|---|
| Up to 200 kW | €80/MWh | €0–40/MWh (higher when market prices are low) | PV in central regions +€4/MWh, northern +€10/MWh |
| 200–600 kW | €70/MWh | €0–40/MWh | Same |
| Over 600 kW | €60/MWh | €0–40/MWh | Same |
Municipalities under 5,000 inhabitants had access to a PNRR grant covering 40% of capital costs for plants up to 1 MW; the grant halves the premium. Applications closed on 31 March 2025 and plants had to be operating by 30 June 2026.
The European Court of Auditors gives a real example: La Buona Fonte, founded in 2021, installed a 19 kW solar plant on an abandoned school producing 20 MWh a year; a third of the energy is shared among 25 members, and the €1,500 of 2024 revenue went to social projects.
Lesson for Ukraine: a dedicated support scheme (premium or grant) gives a transparent incentive without mixing it into the network tariff. It needs a budget and oversight, so in Ukraine it should complement a cost-reflective tariff rather than replace it.
Other examples
Slovenia. The EU ManagEnergy programme describes a “weekend energy community”: a business zone with surplus solar at weekends shares it with a nearby hospital whose demand is higher exactly then. Community value comes from matching profiles, not generation alone.
The EU as a whole. More than 8,000 communities exist, but the European Court of Auditors found that of four audited countries only Italy had fully transposed both directives’ provisions, while unclear definitions and connection delays slow progress.
What Ukraine should take
| Mechanism | Where it works | How to apply it in Ukraine |
|---|---|---|
| Proximity zones by topology | Austria, Italy, Spain | The DSO confirms which substation, feeder or transformer a metering point belongs to (proposal GEO-SUP-08) |
| 15-minute interval metering | Austria, Spain (hourly) | One data resolution in the Metering Code (proposal GEO-04) |
| Agreed allocation algorithm | Spain, Austria | Algorithm in the charter with versions and effective dates (draft p. 10.3.10, GEO-03) |
| Reduced variable network rate | Austria | A separate NEURC methodology for verified local volumes (GEO-TAR-01, GEO-TAR-02) |
| Designated manager | Portugal (EGAC) | A community’s authorised agent under contract (GEO-SUP-01) |
| Targeted premium or grant | Italy | A separate support scheme, not mixed into the tariff |
Sources
- Energy communities (opens in a new tab) · European Commission
- Directive (EU) 2019/944 (opens in a new tab) · EUR-Lex
- Directive (EU) 2018/2001 (RED II) (opens in a new tab) · EUR-Lex
- Directive (EU) 2024/1711 (opens in a new tab) · EUR-Lex
- Detailwissen: Nahebereich und Netzentgelte (opens in a new tab) · Austrian Coordination Office for Energy Communities
Proximity zones, ElWG dates, SNE-VO, EEG exemptions (page modified 19 Oct 2026).
- Messung und Aufteilung (opens in a new tab) · Austrian Coordination Office for Energy Communities
- Preguntas frecuentes autoconsumo (opens in a new tab) · Spanish Ministry for the Ecological Transition (MITECO)
RD 244/2019, Arts. 3 and 4, Annex I.
- Autoconsumo (opens in a new tab) · ERSE (Portugal)
DL 15/2022; access tariffs on shared energy.
- Regulamento do Autoconsumo (PDF) (opens in a new tab) · ERSE
EGAC (Arts. 3, 6, 9); no losses on shared energy (Art. 39). ERSE states the regulation in force was approved as Regulamento n.º 815/2023.
- CER in pillole (opens in a new tab) · Italian Ministry of Environment and Energy Security (MASE)
- Decalogo CER (opens in a new tab) · MASE
- Energy Communities in Action: Lessons from WSED 2026 (opens in a new tab) · ManagEnergy, 12 Apr 2026
- Special report 10/2026: Energy communities – Potential yet to be fulfilled (opens in a new tab) · European Court of Auditors
Box 1, para. 19 – La Buona Fonte; paras. 06, 11 – findings.
This is an explanatory text by Wesfin, not legal advice. Legal acts are quoted from official texts as of the check date; verify the current version before acting.
Read next
- Learn
Network tariffs by electrical proximity: why a kWh from the next-door substation should not cost the same as one from across the country
The Wesfin concept: differentiated network charges for communities depending on whether energy stays within one 0.4 kV substation, one 10 kV feeder or the regional grid. Rationale, safeguards and EU examples.
- Learn
Why Ukraine needs energy communities
The economic, social and technological case for community energy in Ukraine, and the three conditions without which communities will not work.
- Regulation
Reforms needed: an agenda for energy communities in Ukraine
What must change, and in what order, for communities to work: adopt the NEURC procedure, open DataHub data, introduce proximity tariffs, define roles. Wesfin proposals with references.